How to extract project delay from database in Power BI
How to extract project delay from database in Power BI
Beyond forecasted dates, you can calculate project delay directly from schedule updates.
Data Source: Use the total float field from the updates query.
Default Behavior: Power BI returns the sum, but thatβs not useful for delay.
Correct Approach: Select the minimum value β the lowest float represents the true project delay.
Example: If the minimum float is β7, the project is 7 days behind.
Presentation: Add a card visual, rename the title (e.g., Forecasted Delay), and display the "minimum" float.