Adding variance gauge in your project control dashboard

 

Adding variance gauge in your project control dashboard

The Variance indicator is about measuring actual progress against planned targets.

Power BI’s gauge visualization makes this comparison clear.

Cost Variance:

Actual percentage (Earned Value Cost).

Target percentage (cumulative planned cost, based on early dates).

Labor Variance:

Actual percentage (Earned Value Labor Units).

Target percentage (cumulative planned labor units, early dates).

Visualization: Gauge charts display actual vs. planned side by side, with color coding for clarity.

Flexibility: Switch between cost and hours to see performance across different dimensions.